防水材料使用方法
防水材料使用方法
Usage of waterproof materials
搅拌:先将液料倒入容器中,再将粉料慢慢加入,同时充分搅拌3-5分钟至形成无生粉团和颗粒的均匀浆料即可使用;(最好使用搅拌器)。
Mixing: first pour the liquid into the container, then slowly add the powder, and at the same time fully mix for 3-5 minutes until a uniform slurry without raw powder and particles can be used (it is better to use the mixer).
涂刷:用毛刷或滚刷直接涂刷在基面上,力度使用均匀,不可漏刷;一般需涂刷2遍(根据使用要求而定),每次涂刷厚度不超过1mm;前一次略微干固后再进行后一次涂刷(刚好不粘手,一般间隔1-2小时),前后垂直十字交叉涂刷,涂刷总厚度一般为1-2mm;如果涂层已经固化,涂刷另一层时先用清水湿润。
Brushing: brush directly on the base surface with a brush or roller brush, with even force and no missing brush; generally, brush twice (depending on the use requirements), with the thickness not more than 1mm each time; brush the last time after the previous time is slightly dry and fixed (just do not stick to the hand, generally every 1-2 hours), with the front and rear vertical cross brushing, with the total thickness of 1-2mm; if the coating has been cured, paint Wet the other layer with water first.
养护:施工24小时后建议用湿布覆盖涂层或喷雾洒水对涂层进行养护。
Maintenance: after 24 hours of construction, it is recommended to use wet cloth to cover the coating or spray spray to maintain the coating.
检查(闭水试验):卫生间、水池等部位请在防水层干固后(夏天至少24小时,冬天至少48小时)储满水48小时以检查防水施工是否合格。轻质墙体须做淋水试验。
Inspection (closed water test): after the waterproof layer is dry and fixed (at least 24 hours in summer and 48 hours in winter), the toilet, pool and other parts shall be filled with water for 48 hours to check whether the waterproof construction is qualified. Water spraying test shall be conducted for light wall.