平屋面防水施工工艺标准
Waterproof construction technology standard for 1. flat roof
一、工艺流程
1. Process flow
1、适用范围
1. Scope of application
平屋面SBS卷材防水与聚氨脂涂膜组合防水层施工。
Construction of flat roofing SBS coil waterproof and polyurethane coating combined waterproof layer.
2、工艺流程
2. Process flow
基层处理→聚氨脂防水层施工→闭水试验→保护层施工→炉渣找坡层→找平层施工→SBS防水卷材施工→苯板保温层施工→刚性层施工。
The construction of grass-roots treatment, polyurethane waterproof layer
construction, closed water test, protection layer construction, slag
finding slope layer, leveling layer construction, SBS waterproof roll
construction, benzene plate insulation layer construction, and rigid
layer construction.
3、基层处理
3. Grass-roots processing
(1)出屋面管道、烟道、落水口等安装完成,并采用细石混凝土吊洞;女儿墙等出屋面墙体应在防水完成高度处留出泛水槽。完成后对屋
缆接地箱 隔离墩模具 保定电动门 铜狮子 u型槽模具 SMT贴片焊接 收费岛模具 水泥井模具骨面结构板进行24小时闭水;如发现混凝土结构有裂缝,应对裂缝进行修补。
(1) the installation of roofing pipe, flue, water drop port and so on,
and fine stone concrete hanging holes; the wall of the parapet wall
should be left out of the water tank at the completion height of the
waterproof. After completion, the roof structure panel will be closed
for 24 hours. If cracks are found in the concrete structure, cracks
should be repaired.