平屋面SBS卷材防水与聚氨脂涂膜组合防水层施工。
Construction of flat roofing SBS coil waterproof and polyurethane coating combined waterproof layer.
2、工艺流程
2. Process flow
基层处理→聚氨脂防水层施工→闭水试验→保护层施工→炉渣找坡层→找平层施工→SBS防水卷材施工→苯板保温层施工→刚性层施工。
The construction of grass-roots treatment, polyurethane waterproof layer
construction, closed water test, protection layer construction, slag
finding slope layer, leveling layer construction, SBS waterproof roll
construction, benzene plate insulation layer construction, and rigid
layer construction.
3、基层处理
3. Grass-roots processing
(1)出屋面管道、烟道、落水口等安装完成,并采用细石混凝土吊洞;女儿墙等出屋面墙体应在防水完成高度处留出泛水槽。完成后对屋面结构板进行24小时闭水;如发现混凝土结构有裂缝,应对裂缝进行修补。
(1) the installation of roofing pipe, flue, water drop port and so on,
and fine stone concrete hanging holes; the wall of the parapet wall
should be left out of the water tank at the completion height of the
waterproof. After completion, the roof structure panel will be closed
for 24 hours. If cracks are found in the concrete structure, cracks
should be repaired.
(2)平立面交接处、转折处、阴阳角、管根等均应做成均匀一致、平整光滑的圆角,圆弧半径不小于50mm;在楼板混凝土面应清理干净,不平的应采用1:3水泥砂浆找补平。
(2) the intersection, turning point, yin-yang angle, Guan Gen and so on
should be made into uniform, smooth and smooth rounded corners, the
radius of the arc is not less than 50mm; the concrete surface should be
cleaned up in the floor of the floor, and the uneven 1:3 cement mortar
should be used for leveling.
(3)将基层清扫干净,基层应平整、清洁干燥,立墙面不得出现空鼓、开裂返沙等现象。
(3) the base should be smooth, clean, clean and dry, vertical wall may
not appear hollowing and cracking phenomenon of return sand.
4、聚氨脂防水涂料
4, polyurethane waterproof coating
(1)阴阳角部位、管洞周边采用1.2mm厚200mm宽同种类聚氨酯涂膜作为加强层。
(1) 1.2mm is 200mm thick and the same kind of polyurethane coating is
used as reinforcing layer around Yin Yang corner and pipe hole.
(2)立墙面、地面分多遍均匀涂刷1.2厚双组份非焦油聚氨脂(Ⅱ型)防水涂料,上口必须进入泛水槽。
(2) evenly erect 1.2 thick two component non tar polyurethane (II)
waterproof coating on the wall and ground, and the upper part must enter
the flume.
5、闭水试验
5. Water closed test
JS完成后,应闭水24小时,检查防水质量。如出现漏水,应修补后方可隐蔽。
After completion of the JS, the water should be closed for 24 hours to
check the waterproof quality. If leakage occurs, it should be mended and
concealed.
6、按图纸设计要求做1:3水泥砂浆20 mm 厚JS防水保护层、炉渣找坡层及找平层,找平层表面应压光。平立面交接处、转折处、阴阳角、管根等均应做成均匀一致、平整光滑的圆角,圆弧半径不小于50mm。
6, according to the design requirements of the drawings, 1:3 cement
mortar, 20 mm thick JS waterproof protection layer, slit finding layer
and leveling layer shall be made, and the surface of the leveling layer
should be pressed. The facades, turning points, Yin Yang angles, and
pipe roots should be made evenly and smoothly. The radius of the arc
should be no less than 50mm.
7、涂刷冷底子油
7. Paint cold bottom oil
冷底子油要涂刷均匀,不得漏底,干燥后方能进行卷材施工。
Cold base oil should be applied evenly, no leakage, drying and rear for coil construction.
8、SBS卷材附加层
8, SBS coiled material additional layer
平立面交接处、转折处、阴阳角处,需设置500 mm宽附加层卷材,平立面平均展开。
At the junction of the facade, turning point and Yin Yang corner, a 500
mm wide additional layer of coiled material should be set up, and the
flat surface should be expanded on average.
9、SBS卷材大面施工
9, SBS large surface construction
(1)卷材厚度3mm,采用热熔法施工,与基层满粘。
(1) coiled material thickness is 3mm, which is constructed by hot melt method and sticky with the base.
(2)SBS卷材长边短边搭接长度均为不小于100mm,搭接范围必须焊接牢固,接口应溢出热熔的沥青,并将接口封死。
(2) the long lap and short side lap length of SBS coiled material is not
less than 100mm, and the bonding area must be firmly welded. The
interface should overflow hot melt asphalt and seal the interface.
(3)卷材上口必须全部收入泛水槽内,并
纤维 驱鸟设备 保定通风管道 塑料土工格栅 检查井模具 流水槽模具 锻造厂家 华尔街铜牛固定牢固,采用油膏封闭。泛水槽最低不得低于屋面完成后最高处以上250mm。落水口部位应做特殊处理。
(3) the coil must be fully collected in the pan, and it must be firmly
fixed and ointment closed. The minimum of the pan flume shall be less
than 250mm above the roof. Special treatment should be done at the site
of water drop.